Delta-P

Delta P Inc.

The Philippine-based power provider Delta P, Inc. needed to build a power plant with an output of at least 26.65MW. Wärtsilä provided a solution to build a 30MW power plant based on relocated equipment consisting of four Wärtsilä 18V32 generating sets including auxiliaries. The relocation project was offered on an EPC basis, meeting contractual obligations such as a guaranteed completion date and performance guarantees.

Read more about the case (PDF)

Our best option, as it were, was to build a plant with relocated engines. We could not get a better company to do this than Wärtsilä, who originally manufactured them.

Mark Ferrer, Project Manager at Gigawatt Power Inc.

Challenge

Relocating a planned power plant with used engines and auxiliaries as an EPC contract with total responsibility

Solution

Inspection and overhauls of existing gensets and auxiliaries

Engineering and Supply of Balance of Plant equipment

EPC installation and commissioning for four Wärtsilä 18V32 engines including civil works

Benefits

A single vendor for the overhauls, installation and commissioning of the plant

Cost savings when compared to an entirely new power plant

Reliability of power

Guaranteed output

Contact us

Please fill in the form, we aim to respond within 1-2 business days depending on the enquiry. For an existing installation, provide all necessary details to identify the installation and the equipment. Fields indicated with an asterisk (*) are required.