Two field engineers looking at a laptop in an engine hall
Wärtsilä Operation and maintenance

Protect your investment

Operation and maintenance

An operation & maintenance solution with Wärtsilä means entering into a partnership, agreeing on and working towards shared productivity and profitability goals for your company. It is an efficient business solution covering every aspect of the day-to-day operation and all related maintenance and administration tasks. It aims to maximize the productive lifetime of your installation and the return on your investment. The solution is tailored to your specific needs including performance and lifecycle cost guarantees.

Key benefits

  • Wärtsilä responsible for operation & maintenance
  • Lifecycle cost guarantee
  • Risk management
  • Optimised operation and guaranteed performance
  • Maximised productive lifetime of the power plant
  • Maximised return on investment
  • Continuous performance improvement proposals
Two engineers working in a engine hall

Wärtsilä Expertise Centres serve you all the way

The seven Expertise Centres located around the world provide operational support and maintenance management and analytics. Altogether the services provided by Expertise Centres enable the full potential of assets to be realised, as well as guaranteed performance, operational efficiency and optimised maintenance of the plant.

Learn more here: Remote support and data management

Graphic Power Plant

References

  • Gulf Power Limited

    A 10-year Operation and maintenance agreement enables the customer to fulfil power-selling obligations.

    Read more
    Gulf Power Limited
  • Cemex, Colombia

    Renewal of long-term O&M agreement with CEMEX.

    Read more
    Cemex-picture

News

Wärtsilä power plant will provide critical grid balancing as UK expands its renewable energy supply

May 28, 2024, 11:00 by Wärtsilä Corporation

Technology group Wärtsilä is supplying a 48 MW peaking power plant to support the growing use of renewables in the United Kingdom. The plant is under construction and is delivered under an engineering, procurement and construction (EPC) contract with British energy services and solutions company Centrica Distributed Generation Ltd. The order was booked by Wärtsilä in June 2023.

When completed, the plant will provide essential grid balancing power generation alongside an existing 49 MW peaking plant in Brigg, Lincolnshire. This will create nearly 100 MW of fast response assets capable of meeting demand when renewable generation is insufficient. The new plant will operate with four Wärtsilä 31SG gas engines. The fast-starting Wärtsilä engines can reach full output within as little as 2,5 minutes with no minimum up or down time, thus making them ideal for compensating the intermittent supply from wind and solar power.

Chris O’Shea, group chief executive of Centrica, said: "Everything we do is aimed at ensuring our customers have the energy they need, when they need it, at the cheapest price possible. While the UK has made amazing progress towards a renewable energy future, gas plays an essential role in ensuring homes and businesses have access to a reliable electricity supply when the wind doesn’t blow and the sun doesn’t shine. So, we’re delighted to be expanding the Brigg energy park to help balance the increasing renewables on the grid."

The new plant is expected to be fully operational in early 2025. Once connected to the grid, the plant will have the capacity to power 20,000 homes for a full day when required. The high performance Wärtsilä engines with their best-in-class life cycle cost will provide stable and reliable power to the grid.

"We are extremely pleased to support Centrica in their efforts to decarbonise power production. This installation will help enable the use of clean renewable energy by providing the needed grid balancing. The Wärtsilä 31 engine platform is renowned for its high efficiency, and the engines are already able to run on a hydrogen blend. In the future our engines can be converted to run on sustainable fuels once they become widely available," commented Kenneth Engblom, Vice President Africa & Europe at Wärtsilä Energy.

Wärtsilä 31SG gas engine

Media contact for more information on this release:

Katri Pehkonen
Communications Manager
Wärtsilä Energy
Mob: +358 50 591 6180
katri.pehkonen@wartsila.com

Image caption: Wärtsilä is supplying a 48 MW peaking power plant to support the growing use of renewables in the United Kingdom.
© Centrica

All Wärtsilä releases are available at www.wartsila.com/media/news-releases and at news.cision.com/wartsila-corporation where also the images can be downloaded. Use of the image(s) is allowed only in connection with the contents of this press release. Wärtsilä images are available at www.wartsila.com/media/image-bank.

Wärtsilä Energy in brief
Wärtsilä Energy is at the forefront of the transition towards a 100% renewable energy future. We help our customers and the power sector to accelerate their decarbonisation journeys through our market-leading technologies and power system expertise. Our solutions include flexible engine power plants, energy storage and optimisation technology, and services for the whole lifecycle of our installations. Our engines are future-proof and can run on sustainable fuels. Our track record comprises 79 GW of power plant capacity, of which 18 GW are under service agreements, and over 125 energy storage systems, in 180 countries around the world.
www.wartsila.com/energy

Wärtsilä in brief
Wärtsilä is a global leader in innovative technologies and lifecycle solutions for the marine and energy markets. We emphasise innovation in sustainable technology and services to help our customers continuously improve environmental and economic performance. Our dedicated and passionate team of 17,800 professionals in more than 280 locations in 79 countries shape the decarbonisation transformation of our industries across the globe. In 2023, Wärtsilä’s net sales totalled EUR 6.0 billion. Wärtsilä is listed on Nasdaq Helsinki.
www.wartsila.com

Wärtsilä. Let's connect.